Hey Everyone!
I was trying to work on my MS Project File for a Construction Project and had some questions.
I am trying to apply some conditional formatting to compare the data in two different cells. If the "Material Lead Time" Finish Date exceeds the "First Install" start date, I need to turn the lead time cell red (or add a graphical symbol similar to what is shown in the 1 week/2 week column).
The first install start date is being carried over from the original task located at row 18.
Any help would be appreciated! Thank you!