We got an application entered under the deadline for nem 2.0 for our solar installation and received our permission to operate from PGE last week.
Today my solar installer sent me a separate interconnection agreement for our Powerwall storage system. My questions are...
Given the timing of all of this, will signing this set my whole account to be now on nem 3.0?
If the answer to the above question is yes, what are the implications of not signing this separate interconnection agreement? Does that just mean I can't export battery storage back to grid during peak times?